The Township's aging sewer forcemain has broken repeatedly, and the Board awarded a $2.77 million contract to replace it, funded by a PENNVEST loan repaid from sewer revenue plus a $500,000 state grant.
At a glance
- Total mentions
- 3
- Last 30 days
- 1
Last discussed Mar 10, 2026.
Impact analysis
The $2.77 million project will be paid back through sewer revenues, with $500,000 offset by a state grant.
Sewer customers in the Kearsarge area get a more reliable system with fewer breaks.
Mentions & discussions (3)
Erie, Crawford receive over $13 million for water infrastructure projects
(WJET/WFXP)-- More than $13 million is on its way to Erie and Crawford counties to help make sure residents have safe and clean drinking water. Elected officials from both counties announced the latest round of PENNVEST funding to replace roughly 1,2...
Board of Supervisors (Regular) - Mar 10, 2026
The Township's aging sewer forcemain has broken repeatedly, and the Board awarded a $2.77 million contract to replace it, funded by a PENNVEST loan repaid from sewer revenue plus a $500,000 state grant.
Board of Supervisors (Regular) - Jan 27, 2026
Millcreek is borrowing up to $3.76 million at a low 1% interest rate from PENNVEST, backed by a $500,000 state grant, to fix long-standing maintenance issues on the Kearsarge Force Main sewer line.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Millcreek Township
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.